Risk Response Plan¶
At a glance
- Purpose: Turn each significant risk into a named response with an owner, a trigger, and a cost — so that responding is a decision made in advance rather than a reaction under pressure.
- Use it when: For every risk above the project's agreed threshold, after assessment. It is the second half of the risk register and the input to contingency planning.
- Owner: The named risk owner for each response, not the project manager for all of them.
- Related: Module 08 · Lab 17
How to use this template¶
- Write the response as a verb with an object — "prototype the record-matching with the records office's sample data" — not as an intention like "monitor closely".
- Name the strategy explicitly. The five are avoid, transfer, mitigate, accept, and escalate, and naming one forces the question "is this really the best we can do?".
- Define the trigger: the observable event that says the risk is happening. A risk with no trigger is discovered by surprise, and by then the response costs more.
- Put a cost and a date against the response. A response without a budget competes with everything else for unallocated time and will lose.
- Carry a contingency reserve for accepted risks, sized from their expected exposure, and state who may release it.
Field descriptions¶
| Field | What goes in it | Watch out for |
|---|---|---|
| Risk ID | The ID from the risk register | Responses without an identified risk |
| Risk (short) | Cause → effect, kept brief | Restating the whole register row |
| Strategy | Avoid / transfer / mitigate / accept / escalate | "Mitigate" for everything |
| Response actions | Concrete steps with owners and dates | Verbs like "consider" or "ensure" |
| Trigger | The observable signal that the risk is occurring | A trigger nobody is watching for |
| Residual exposure | Probability × impact after the response | Assuming responses are fully effective |
| Response cost | Money or time the response consumes | Ignoring the cost of the response itself |
| Contingency | Reserve held in case the risk occurs | Contingency with no release authority |
| Fallback | What happens if the response fails | No plan B for the highest exposure |
Blank template¶
# Risk Response Plan — [Project name]
| | |
| --- | --- |
| **Version** | [1.0] |
| **Threshold for planning a response** | [e.g. exposure of 6 or more on the 1–3 × 1–3 scale, or any risk to a legal obligation] |
| **Contingency reserve** | [Amount of money and time, and who authorises release] |
| Risk ID | Risk (short) | Strategy | Response actions | Owner | Trigger | Residual P × I | Response cost | Fallback |
| --- | --- | --- | --- | --- | --- | --- | --- | --- |
| R-01 | [Cause → effect] | Mitigate | [Steps] | [Who] | [Observable signal] | [p × i] | [Cost] | [If the response fails] |
## Reserve sizing
| Risk ID | Exposure if it occurs | Probability | Expected cost | Included in reserve? |
| --- | --- | --- | --- | --- |
| R-01 | [Impact in money or days] | [p] | [p × impact] | Yes / No — accepted |
## Release authority
| Reserve band | Who may release it | Escalation if exceeded |
| --- | --- | --- |
| Up to [X] | [Project manager] | [Sponsor] |
## Review and closure
| Date | Risk ID | Status change | Reason |
| --- | --- | --- | --- |
| | R-01 | Closed / Occurred / Still open | [Evidence] |
Worked example¶
From Lab 17, on the admission portal — invented figures for teaching. Four risks, four different strategies:
| Risk ID | Risk | Strategy | Response | Trigger | Residual | Cost |
|---|---|---|---|---|---|---|
| R-01 | The eligibility rule set is not agreed with the admissions office before build starts → rework of the rules engine | Avoid | Sequence the rules engine after written sign-off; build only the submission path until then | Sign-off not obtained by the design milestone | 2 × 3 = 6 (was 3 × 5 = 15) | 1 week of resequenced effort |
| R-02 | Security review queue delays the integration → schedule slip on the critical path | Transfer | Contract the review to a certified external assessor with a 10-day service commitment | Review request not acknowledged within 3 days | 3 × 3 = 9 (was 3 × 5 = 15) | External fee, agreed in advance |
| R-03 | Applicant data retention period is not confirmed → compliance exposure | Mitigate | Implement retention as configuration; obtain the confirmation in parallel | Records office declines to confirm by the data-model milestone | 2 × 5 = 10 | 3 days of configuration work |
| R-04 | Peak load during the admission window exceeds current capacity | Accept | No change to the design; monitor and scale operationally | Sustained response times above the agreed threshold | 3 × 3 = 9 | Reserve held, not spent |
Two lessons are worth pulling out. First, R-02 is the only risk where the response costs money and is still correct, because the exposure sits on the critical path — see Lab 10 for why external queue time is critical here. Second, R-04's honest answer is "accept": the response is monitoring plus a reserve, and pretending otherwise would consume effort for no reduction in exposure. Lab 17's exercise is precisely to argue which risks deserve which strategy, and to show that accept is a strategy, not an omission.
Common mistakes¶
- "Monitor closely" as a response. It is not a response; it is a decision not to respond, which may be fine — but say accept and hold a reserve.
- Mitigation for everything. It conceals opportunities to avoid the risk entirely or transfer it.
- No trigger. Without an observable signal, the response begins only after the impact is felt.
- Ignoring the response's own cost and new risks. Reducing a schedule risk by fast-tracking introduces a rework risk, which belongs in the register.
- Contingency that is really a buffer already spent. If the reserve is inside the baseline, it cannot absorb anything.
- Assigning every risk to the project manager. Risk owners should be the people who can actually act.
- No fallback for the largest exposure. For high-impact risks, the fallback is the plan that matters when the mitigation fails.