Risk Assessment Matrix¶
At a glance
- Purpose: Give everyone the same way of judging how serious a risk is, so scores are comparable, arguments are about evidence rather than adjectives, and thresholds mean something.
- Use it when: During risk assessment, and again to compare residual exposure after responses. It is the scoring rule behind the risk register.
- Owner: The project manager defines the scales; the project team and sponsor agree them.
- Related: Module 08 · Lab 11 · Lab 17
How to use this template¶
- Agree the scales before scoring anything. The value of the matrix is that a score means the same thing whoever assigns it.
- Anchor each level to something concrete — a duration, a cost band, a legal consequence — not to adjectives. "High impact" is an opinion; "delays a milestone by more than two weeks" is a test.
- Score in two steps: probability first, then impact. Scores agreed in one step drift toward the assessor's general feeling about the project.
- Apply the threshold consistently: risks at or above it need a named owner and a written response, and the same threshold must be used at every review.
- Re-score residual exposure after the response. A matrix used only once, at identification, tells you the weather on one day.
Field descriptions¶
| Field | What goes in it | Watch out for |
|---|---|---|
| Probability level | A percentage band, with the words that go with it | Precise-looking percentages with no basis |
| Impact levels | Bands per dimension: schedule, cost, quality, legal | A single impact scale for all dimensions |
| Exposure | The product (or a lookup grid) of the two | Averaging instead of multiplying |
| Threshold | The score above which a response is mandatory | A threshold nobody applies |
| Residual | Exposure after the response | Assuming total effectiveness |
| Opportunity scale | The mirror image, for upside risks | Registers with only threats |
Blank template¶
# Risk Assessment Matrix — [Project name]
| | |
| --- | --- |
| **Version** | [1.0] |
| **Agreed with** | [Sponsor, team] |
## Probability scale
| Level | Label | Working definition |
| --- | --- | --- |
| 1 | Low | Unlikely during the project; no current evidence it will occur |
| 2 | Medium | Plausible; some evidence, or it has happened on comparable work |
| 3 | High | Likely; current conditions point to it occurring |
## Impact scale
| Level | Schedule | Cost | Quality or legal |
| --- | --- | --- | --- |
| 1 | Under one week of slip, recoverable within float | Under [x]% of budget | Cosmetic; no user-visible effect |
| 2 | One to two weeks of slip | [x–y]% of budget | User-visible defect, workaround exists |
| 3 | More than two weeks, or on the critical path | Above [y]% of budget | Regulatory or contractual breach; release blocked |
## Exposure grid
Exposure = probability × impact. Any risk scoring **6 or above** requires a named owner and a written
response, and is reported to the sponsor.
| Probability ↓ / Impact → | 1 | 2 | 3 |
| --- | --- | --- | --- |
| **1 — Low** | 1 | 2 | 3 |
| **2 — Medium** | 2 | 4 | **6** |
| **3 — High** | 3 | **6** | **9** |
Bold cells are at or above the threshold.
## Scale for opportunities
| Level | Probability | Benefit |
| --- | --- | --- |
| 1–3 | As above | [Bands, mirroring the impact scale] |
## Assumptions and limitations
- [e.g. Scores are ordinal. A risk scoring 9 is not three times as important as one scoring 3.]
- [e.g. The cost bands are relative to this project's budget, and must be re-anchored for another one.]
## Review record
| Date | Change | Reason |
| --- | --- | --- |
Worked example¶
Two risks from Lab 11 scored with these scales, invented figures for teaching:
| Risk | Probability | Impact | Exposure | Verdict |
|---|---|---|---|---|
| Security review queue delays the integration by three weeks | 3 (High — the queue is currently 12 deep) | 3 (critical path, so more than two weeks) | 9 | Above threshold: named owner, written response, reported |
| Retention period confirmation is late | 2 (Medium) | 3 (legal consequence if configured wrongly) | 6 | At threshold: response required |
| A team member takes unexpected leave | 2 (Medium) | 1 (under a week, inside float) | 2 | Below threshold: accepted and monitored |
| The vendor offers an unused licence tier at no cost | 1 (Low) | 2 (reduces licence cost) | 2 | Opportunity, recorded, low priority |
Two points the grid shows that prose does not. The legal risk scores 6 despite only medium probability, because impact alone can carry a risk over the threshold — a project that triages on probability will miss it. And the third row's low score is a deliberate accept: at exposure 2, spending a week to reduce it would cost more than the risk itself. That comparison — response cost against exposure — is the judgement the matrix exists to support, not to replace.
Common mistakes¶
- Unanchored scales. If nobody can say what "impact 2" means in days or money, scores are opinions with numbers attached.
- Multiplying across dimensions. A single impact level that mixes schedule, cost, and legal effect cannot be compared between risks; score the dimension that drives the response.
- Treating exposure as a measurement. It is ordinal and comparative, not arithmetic — see the limitation note above.
- A threshold that is not enforced. If risks above the line have no owner, the matrix is decoration.
- Scores that never change. A register whose risk scores are identical at identification and close has not been reviewed.
- Threats only. Omitting opportunities systematically biases the project toward pessimism and hides cheap wins such as reusing an existing component.
- No residual column. Without it, you cannot tell whether the response achieved anything.