Feasibility Assessment

At a glance

  • Purpose: Decide whether a project can be done — technically, operationally, financially, legally, and in the time available — before committing to it.
  • Use it when: Between the business case and the charter, and again if a major constraint changes. Feasibility answers "can we?", not "should we?" and not "will we?".
  • Owner: The project manager or a small assessment team, with each dimension owned by the person who can judge it.
  • Related: Module 02 · Lab 04

How to use this template

  1. Assess five dimensions separately. A project is often feasible on four and blocked on the fifth, and it is the blocked one that decides.
  2. For each dimension, state the verdict (feasible / feasible with conditions / not feasible) and the evidence — not an opinion.
  3. Name the condition that would change a verdict. Feasibility assessments that say "yes" or "no" without naming the condition cannot be acted on.
  4. Identify the single binding constraint — the one that governs the others — and test it first.
  5. Record what you would have to not do to make an infeasible dimension feasible. That is usually a scope trade, and it belongs in the recommendation.
  6. Keep it short. A feasibility assessment is a decision aid, not a research report.

Field descriptions

Dimension What it asks Evidence to look for
Technical Can it be built with available technology and skills? A prototype, a spike, a vendor's documented capability, a named person who has done it
Operational Will the organisation be able to run it and change its processes? Staff availability, training needs, process ownership, support model
Financial Is the money available, and is the case positive? Budget authority, lifetime cost, funding source for operations
Legal and regulatory Is it permissible, and what obligations attach? The current version of the applicable rule, confirmed with the responsible office
Schedule Can it be delivered in the time available? Capacity arithmetic, external lead times, dependency on others' queues
Binding constraint Which of the above governs the rest? The one where relaxing it changes every other verdict

Blank template

# Feasibility Assessment — [Project name]

| | |
| --- | --- |
| **Assessed by** | [Names and roles] |
| **Date** | [YYYY-MM-DD] |
| **Recommendation** | [Proceed / Proceed with conditions / Do not proceed / Return for re-scoping] |

## 1. Technical feasibility

| | |
| --- | --- |
| **Verdict** | [Feasible / Feasible with conditions / Not feasible] |
| **Evidence** | [Prototype result, prior project, vendor documentation, named expertise] |
| **Condition that would change this** | [Specific and observable] |
| **Unknowns** | [What you could not determine, and how you would determine it] |

## 2. Operational feasibility

[Same four fields. Address who will run it, how their process changes, and whether they have
agreed to it.]

## 3. Financial feasibility

[Same four fields. Cover total cost of ownership, not only build cost, and name the budget
holder who has confirmed availability.]

## 4. Legal and regulatory feasibility

[Same four fields. State which specific requirement applies and who confirmed its current
version. Do not state a legal position you have not verified.]

## 5. Schedule feasibility

[Same four fields. Include the capacity arithmetic and any external lead time or queue.]

## 6. The binding constraint

[Which dimension governs the others, and why. What would have to change for the project to
become feasible, and what would that change cost?]

## 7. Recommendation

[Proceed / proceed with conditions / return for re-scoping / do not proceed — with the
conditions listed. If the answer depends on a scope reduction, say which scope.]

## 8. Conditions to be met before the charter is signed

| # | Condition | Owner | Due |
| --- | --- | --- | --- |
| 1 | [Condition] | [Role] | [YYYY-MM-DD] |

Worked example

A partial assessment of the campus event portal from Lab 01, with assumptions invented for teaching:

Dimension Verdict Evidence Condition
Technical Feasible Standard web application; single sign-on already used elsewhere Reuse the existing authentication library rather than build one
Operational Feasible with conditions IT office has agreed to host; moderation process not yet agreed Staff moderation workflow agreed before launch
Financial Feasible Within the director's delegated budget None
Legal Feasible with conditions Event listings and images involve publishing rights Confirm image-consent approach with the records office
Schedule Feasible with conditions One developer at one day per week against roughly 20 person-days Security review booked in week 1, not week 8

The binding constraint is schedule, because it is the dimension that would force the others to change: a shorter runway would remove the moderation workflow and the image-consent step from the release, and technical feasibility depends on the security review having time.

Common mistakes

  • Assessing only the technical dimension. Most failures are operational, financial, or legal, and technical feasibility is the easiest to confirm.
  • Verdicts with no evidence. "The team can build it" is not evidence; a prototype or a named experience is.
  • Stating legal conclusions you have not verified. Say which office confirmed the requirement, and when.
  • Treating feasibility as permanent. It changes when technology, budget, regulation, or capacity changes — reassess if a major constraint moves.
  • Answering "should we?" That is the business case. Feasibility is only about whether it can be done.
  • No conditions. An unconditional "feasible" gives the project no protection when the condition fails.