Business Case¶
At a glance
- Purpose: Justify a project in business terms — why do it, what it costs, what it returns, and what happens if you do nothing.
- Use it when: Before a charter exists, when someone must decide whether to fund the work. Also when scope or cost changes enough to re-open that decision.
- Owner: Usually the sponsor or business owner; the project manager contributes the delivery estimates.
- Related: Module 02 · Lab 13
How to use this template¶
- Write the problem and the options before writing the costs. A business case that starts from a chosen solution is a justification, not an assessment.
- Include at least two alternatives, one of which is do nothing. A single-option case cannot be evaluated.
- Estimate costs and benefits as ranges with the assumptions stated. See Lab 13 for the method.
- Make the benefit measurable and name who will measure it. A benefit nobody measures is a claim.
- State the recommendation and what would change it. A case with no reversal condition cannot be challenged, which usually means it has not been thought about.
Field descriptions¶
| Field | What goes in it | Watch out for |
|---|---|---|
| Problem or opportunity | What is going wrong today, for whom, and what it costs | Describing a missing feature as the problem — that is a solution |
| Strategic fit | Which organisational objective this serves | Claiming every objective; pick the ones that actually apply |
| Options considered | At least two, plus "do nothing" | Options that are obviously worse, included to make one look good |
| Option description | What each option delivers, at what scale | Detail that belongs in a scope statement |
| Costs | Build and operate, as a range, with basis and assumptions | Build cost only — the cheapest part of a system's life |
| Benefits | What improves, by how much, who measures it, when | Unmeasured benefits, or benefits the project cannot influence |
| Risks | The risks that would change the decision | A full risk register — this is not the register |
| Recommendation | Which option, and why, in one paragraph | Restating the options instead of choosing |
| Reversal conditions | What would make you withdraw the recommendation | "If things change" — too vague to act on |
| Decision and date | Who decided, when, and what they approved | A blank decision block that stays blank |
Blank template¶
# Business Case — [Project or initiative name]
| | |
| --- | --- |
| **Prepared by** | [Name, role] |
| **Date** | [YYYY-MM-DD] |
| **Version** | [1.0] |
| **Decision required from** | [Who must decide] |
| **Decision by** | [YYYY-MM-DD — the date the decision is needed] |
## 1. Problem or opportunity
[What is going wrong or what opportunity exists, for whom, and what it costs today — in
time, money, risk, or quality. Do not mention a solution here.]
## 2. Strategic fit
[Which organisational objective(s) this serves. If it serves none, say so.]
## 3. Options considered
| Option | Description | Build cost (range) | Operating cost per year | Benefit | Main risk |
| --- | --- | --- | --- | --- | --- |
| A — Do nothing | [What the status quo looks like] | 0 | [Current cost] | — | [The cost of inaction] |
| B — [Option name] | [What it delivers] | [Low – High] | [Range] | [Benefit] | [Risk] |
| C — [Option name] | [What it delivers] | [Low – High] | [Range] | [Benefit] | [Risk] |
## 4. Costs of the recommended option
| Component | Basis | Amount |
| --- | --- | --- |
| Labour | [person-days × rate] | |
| Non-labour | [licences, infrastructure, training] | |
| Contingency (known risks) | [Derived from the risk register] | |
| Management reserve | [Held by the sponsor] | |
| **Total (range)** | | |
**Excluded:** [What is deliberately not costed, e.g. post-launch hosting — and who pays it instead.]
## 5. Benefits
| Benefit | How it is measured | Baseline today | Target | Measured by | Measured when |
| --- | --- | --- | --- | --- | --- |
| [Benefit] | [Measure] | [Current value] | [Target] | [Role, outside the project] | [Date] |
## 6. Risks that could change the decision
| Risk | If it occurs | Effect on the case |
| --- | --- | --- |
| [Risk] | [What happens] | [Benefit reduced / cost increased / decision reversed] |
## 7. Recommendation
[Which option, in one paragraph, with the strongest single reason.]
## 8. This recommendation should be revisited if
1. [Concrete condition]
2. [Concrete condition]
3. [Concrete condition]
## 9. Decision
| Field | Value |
| --- | --- |
| Decision | [Approved / Approved with conditions / Deferred / Rejected] |
| Decided by | [Name, role] |
| Date | [YYYY-MM-DD] |
| Conditions | [Anything attached to the approval] |
Worked example¶
A partial example for the University LMS used in Lab 03, with invented figures for teaching:
| Option | Build cost | Operating cost per year | Benefit | Main risk |
|---|---|---|---|---|
| A — Do nothing | 0 | 0 | — | Marks remain at risk of loss; reconciliation continues |
| B — Departmental LMS | ≈ PKR 2.7m | ≈ hosting only | Marks in one recoverable place; reconciliation time falls | Adoption by sceptical lecturers |
| C — Buy a commercial product | ≈ PKR 1.2m licence + integration | Licence per year, rising | Faster to launch; more features | Annual cost grows; data held by a vendor |
The completed version would state the measurement for the adoption benefit, name the head of department as the owner, and give three reversal conditions — for example "if the commercial licence cost rises above the departmental budget in year two".
Common mistakes¶
- Starting from the solution. If the options section contains one real option, you have written a proposal.
- Build cost only. Operating and exit costs decide most technology business cases, and they are usually omitted.
- Benefits nobody measures. Name the measurer and the date, or delete the benefit.
- A single number. Ranges with stated assumptions survive scrutiny; a point figure invites argument about the figures instead of the decision.
- Leaving the decision block empty. An undocumented decision will be re-made by someone else, with worse information.
- Treating the case as finished when it is approved. Re-open it if cost or scope changes materially — that is what reversal conditions are for.