Calculators and Worksheets

Six pieces of arithmetic carry most of the quantitative work in this course. This page gives the formula, a worked example, the assumptions behind it, and a command that reproduces the example — so you can check your own spreadsheet rather than trust it.

How to use this page

Work the example by hand first. The command is a checking aid, not a substitute for understanding the arithmetic, and every lab that uses a calculator expects you to show your working.

The calculator tool

tools/spm-calculators.py needs only Python 3 — no packages to install.

python tools/spm-calculators.py --check          # validate every formula against this page
python tools/spm-calculators.py pert 4 6 14      # three-point estimate
python tools/spm-calculators.py schedule --file docs/templates/csv/project-schedule.csv

--check validates 29 known results taken from the worked examples below and from Lab 10, Lab 18, and Lab 21; it runs in the repository's checks, so a formula that contradicts this page fails.


1. Three-point (PERT) estimation

Formula

$$E = \frac{O + 4M + P}{6} \qquad \sigma = \frac{P - O}{6}$$

where $O$ is optimistic, $M$ most likely, and $P$ pessimistic. For several activities in series, expected values add and variances add:

$$E_{total} = \sum E_i \qquad \sigma_{total} = \sqrt{\sum \sigma_i^{2}}$$

Worked example — an 8-day activity where the team is unsure:

Estimate Value Reasoning
Optimistic 4 days Everything works first time
Most likely 6 days The normal case
Pessimistic 14 days The integration behaves as it did last time

$E = (4 + 4(6) + 14) / 6 = 42 / 6 = \mathbf{7 days}$ · $\sigma = (14 - 4) / 6 = \mathbf{1.67 days}$

A second activity estimated $(6, 10, 20)$ gives $E = 11$ and $\sigma = 2.33$. In series:

$$E_{total} = 7 + 11 = \mathbf{18 days} \qquad \sigma_{total} = \sqrt{1.67^2 + 2.33^2} = \mathbf{2.87 days}$$

python tools/spm-calculators.py pert 4 6 14

Assumptions and limitations

  • The weights of 1, 4, 1 are a convention, not a law. They produce a useful weighted average; they do not make the estimate true.
  • The formula treats $O$ and $P$ as realistic bounds. If they are round numbers chosen to widen the range, the resulting standard deviation is meaningless.
  • Independence is assumed. If two activities share the same risk — the same unfamiliar subsystem, the same external queue — their uncertainties are correlated and the combined standard deviation is understated. For a series that shares a risk, treat the shared cause as a separate item.
  • Adding 2σ to a schedule is a planning decision, not a probability guarantee. State the range, then decide.
  • Used in Module 07 and Lab 13.

2. Cost estimation

Formula

$$base = effort \times rate \qquad overhead = base \times overhead\% \qquad subtotal = base + overhead$$

$$contingency = subtotal \times contingency\% \qquad total = subtotal + contingency$$

Worked example — 42 person-days at a day rate, 10% overhead, 5% contingency:

Component Calculation Amount
Base 42 × 45,000 1,890,000
Overhead 1,890,000 × 10% 189,000
Subtotal 2,079,000
Contingency 2,079,000 × 5% 103,950
Total 2,182,950
python tools/spm-calculators.py cost --days 42 --rate 45000 --overhead 10 --contingency 5

Assumptions and limitations

  • The rate must be the all-in cost the organisation uses, and stated as such. Whether it includes supervision, equipment, and leave is the most common source of disagreement between two estimates.
  • Effort is in person-days, not elapsed days. A 42 person-day task done by three people is not necessarily 14 days of calendar time.
  • Contingency is not a padding percentage. It covers identified uncertainty; unexplained padding should be removed and the underlying estimate challenged instead.
  • The order of overhead and contingency changes the answer, so follow the organisation's convention and say which you used. Here contingency applies to the subtotal, not the base.
  • Currency is not handled. All figures must be in one currency at one point in time.
  • Used in Module 07 and Lab 13.

3. Risk exposure

Two distinct uses, which must not be mixed:

Use Formula Meaning
Ranking on the course's 1–3 scale $exposure = P \times I$ (ordinal) A comparative score from 1 to 9 that prioritises attention
Expected monetary value $EMV = p \times impact$ (real units) Money or days, used to size a contingency reserve

Worked example — a risk with a 40% chance and a 500,000 impact: $EMV = 0.4 \times 500{,}000 = \mathbf{200{,}000}$. On the ordinal scale, probability 2 (medium) and impact 3 (high) gives exposure $\mathbf{6}$, at the threshold where a written response is required (see the risk assessment matrix).

python tools/spm-calculators.py risk --probability 0.4 --impact 500000

Assumptions and limitations

  • Ordinal exposure is comparative, not arithmetic. A risk scoring 9 is not three times as important as one scoring 3, and scores cannot be summed into a meaningful total.
  • Expected value is an average over many repetitions. For a single project it is not a prediction, and a low expected value does not justify ignoring a risk whose impact would end the project. That is why the response threshold is set by impact as well as score.
  • Multiplying ordinal scores assumes the two are independent, which is convenient rather than true.
  • Expecting every risk to be scored with false precision is worse than a rough ranking. Where a number would be invented, say "not quantified".
  • Used in Module 08 and Lab 17.

4. Earned value management

Formulas

Measure Formula Reading
Cost variance $CV = EV - AC$ Positive = under budget
Schedule variance $SV = EV - PV$ Positive = ahead of plan, in value terms
Cost performance index $CPI = EV / AC$ 1.0 = on budget
Schedule performance index $SPI = EV / PV$ 1.0 = on plan
Estimate at completion $EAC = BAC / CPI$ Forecast cost if current efficiency continues
Variance at completion $VAC = BAC - EAC$ Forecast over- or under-spend
To-complete performance index $TCPI = (BAC - EV) / (BAC - AC)$ Efficiency required from now on

Worked example — a scaled position with the same schedule performance as Lab 18 (SPI 0.80) but a worse cost performance, so the two readings can be compared:

Measure Calculation Result
Cost variance 160,000 − 190,000 −30,000 (over budget)
Schedule variance 160,000 − 200,000 −40,000 (behind plan)
Cost performance index 160,000 / 190,000 0.84
Schedule performance index 160,000 / 200,000 0.80
Estimate at completion 800,000 / 0.8421 950,000
Variance at completion 800,000 − 950,000 −150,000
To-complete performance index 640,000 / 610,000 1.05
python tools/spm-calculators.py evm --pv 200000 --ev 160000 --ac 190000 --bac 800000

Note that SPI 0.80 agrees with a completely different measure in Lab 22: 16 of 20 planned items delivered. Two independent readings agreeing is what makes the figure credible, and a disagreement between them is information worth chasing.

Assumptions and limitations

  • Earned value requires a meaningful baseline and a rule for what counts as "earned" — usually the definition of done. Without both, EV is a guess with three decimal places.
  • A front-loaded baseline distorts SPI, flattering it early and harshly penalising it later. Always read SPI alongside a plain count of days slipped against named milestones (Lab 18 works through exactly this discrepancy).
  • $EAC = BAC / CPI$ assumes current efficiency continues to the end. That is an assumption, not a forecast — if the overrun was a one-off, it is pessimistic; if the cause is systemic, it may be optimistic.
  • Percent-complete measures for work in progress are the least reliable input. Use objective completion criteria, not a developer's estimate of progress.
  • Earned value says nothing about quality. Work can be 100% complete and defective; check the defect log alongside it.
  • Used in Module 11 and Lab 18.

5. Resource capacity

Formula

$$capacity = headcount \times working days \times availability factor \qquad balance = capacity - demand$$

Worked example — one tester, six weeks, and a shared DBA (from Lab 21):

Role Headcount Days Availability Capacity Demand Balance
Backend developer 2 30 0.8 48 42 +6
Frontend developer 1 30 0.8 24 30 −6
DBA (shared) 0.2 30 1.0 6 9 −3
python tools/spm-calculators.py capacity --headcount 1 --days 30 --availability 0.8 --demand 30

Assumptions and limitations

  • The availability factor is a stated assumption, not a measurement. 0.8 is realistic for a person with leave, support duties, and meetings; 1.0 is a planning error that appears later as unexplained slippage.
  • Totals can balance while every period fails. Compute this per period and per skill, never for the project as a whole — that aggregation error is the entire point of Lab 21.
  • Capacity is a ceiling, not a commitment. A shared resource is released the first time the other project has an incident.
  • The tool has no levelling algorithm. Resolving a shortfall is a decision — resequence using float, substitute skills, reduce scope, then negotiate capacity — and it belongs in the plan, not in a formula.
  • Used in Module 10 and Lab 21.

6. Schedule calculations

Method — a forward pass, a backward pass, float, and the critical path:

  1. Forward pass: $ES = \max(EF \text{ of predecessors})$, then $EF = ES + duration$.
  2. Project duration = the largest $EF$ in the network.
  3. Backward pass: $LF = \min(LS \text{ of successors})$, then $LS = LF - duration$; the last activity's $LF$ equals the project duration.
  4. Total float $= LF - EF$ (equivalently $LS - ES$).
  5. Critical path = the chain of activities with zero float.

Worked example — the ten-activity network from Lab 10, which is also the worked example in the project schedule template:

ID Duration ES EF LS LF Float Critical
A 5 0 5 0 5 0 Yes
B 4 5 9 5 9 0 Yes
C 6 9 15 19 25 10 No
D 5 9 14 9 14 0 Yes
E 8 9 17 23 31 14 No
F 6 15 21 25 31 10 No
G 7 14 21 14 21 0 Yes
H 10 21 31 21 31 0 Yes
I 5 31 36 31 36 0 Yes
J 4 36 40 36 40 0 Yes

Duration 40 working days · critical path A → B → D → G → H → I → J. Activity I waits for three predecessors and starts at the largest early finish (31), not the sum.

python tools/spm-calculators.py schedule --file docs/templates/csv/project-schedule.csv

Assumptions and limitations

  • Day 0 is the start. The tool calculates in working days and does not know your calendar — excluding weekends and public holidays is your step, and it is where most date errors occur.
  • Resources are assumed available. This is not resource levelling, and a levelled schedule can be longer than the critical path implies.
  • Float belongs to the project, not to the activity's owner. Spending float on one path can move the critical path.
  • The critical path is only valid for the current durations and logic. Change either and it must be recalculated — a stale critical path is worse than none.
  • Real projects have loops, optional work, and probabilistic durations. This tool handles none of them; it is a checking aid for small networks, not a scheduling package.
  • Used in Module 06 and Lab 09 · Lab 10.

Further practice

  • Every one of these calculators is exercised in a lab, and the labs give the scenario and the data: Lab 13 · Lab 16 · Lab 17 · Lab 18 · Lab 21.
  • The spreadsheet-ready inputs are in the CSV library, whose conventions explain why durations are labelled in working days and estimates carry a basis.
  • Instructor answer keys with the full working are in the answer keys area. Attempt the lab before reading them.