Communications Plan¶
At a glance
- Purpose: Decide in advance who needs which information, in what form and how often — and who escalates what, to whom, within how long.
- Use it when: After the stakeholder register, before delivery starts. It is one of the most frequently skipped plans and one of the most frequently blamed after a failure.
- Owner: The project manager.
- Related: Module 10 · Lab 12
A communications plan decides, in advance, who needs which information, in what form, and how often. It prevents the two common failures: burying people in updates they do not need, and leaving key people uninformed until a problem is unavoidable.
Copy the skeleton below and replace the bracketed text.
Plan skeleton¶
# Communications Plan — [Project name]
| | |
| --- | --- |
| **Date** | [YYYY-MM-DD] |
| **Owner** | [Who] |
## Communication matrix
| Audience | Information | Format | Frequency | Owner | Channel |
| --- | --- | --- | --- | --- | --- |
| [Sponsor] | Progress, risks, decisions needed | Status report | [Fortnightly] | [PM] | [Email] |
| [Team] | Tasks, blockers | Stand-up | [Daily] | [PM] | [Meeting] |
| [Users] | What is changing and when | Release notes | [Per release] | [PM] | [Portal] |
## Escalation
| Situation | Escalate to | Within |
| --- | --- | --- |
| [Missed milestone] | [Sponsor] | [24 hours] |
| [Security concern] | [IT security lead] | [Immediately] |
## Meeting rhythm
| Meeting | Purpose | Attendees | Duration | Frequency |
| --- | --- | --- | --- | --- |
| [Name] | [Purpose] | [Who] | [NN min] | [How often] |
## Ground rules
- [e.g. Decisions are recorded in writing within one working day.]
- [e.g. Anything that changes scope goes through the change process.]
How to use this template¶
- Start from the stakeholder register. Every high-influence stakeholder must appear, and the "what they need" column becomes the information column here.
- Match format to need. A sponsor usually wants a summary and a decision; the team needs detail and blockers; operations needs support implications. One format for everyone serves nobody.
- Name the sender, not just the channel. Unowned updates do not get sent, and unowned meetings do not get agenda items.
- Make escalation concrete: the trigger, the recipient, and the time limit. "Escalate when necessary" means different things to different people, which is discovered at the worst moment.
- Agree the meeting rhythm and the artefacts each meeting produces. A recurring meeting with no output decays into a status round-robin.
- Review it when the project changes phase. Communication needs at initiation and during hypercare are not the same.
Field descriptions¶
| Field | What goes in it | Watch out for |
|---|---|---|
| Audience | A named stakeholder or group | "Everyone" as an audience |
| Information | What they actually need | What you would like to tell them |
| Format | Report, meeting, dashboard, conversation | Slides for a decision that needs a document |
| Frequency | A cadence you can sustain | Daily updates nobody reads |
| Owner (sender) | Who produces and sends it | The PM as sender of everything |
| Channel | Email, portal, meeting, shared board | Channels the audience does not use |
| Escalation trigger | The observable condition | "If things go wrong" |
| Escalation limit | The time within which it must escalate | Nothing, which means never |
Worked example¶
From Lab 12, on the complaint-management system — invented for teaching:
| Audience | Information | Format | Frequency | Owner |
|---|---|---|---|---|
| Service director (sponsor) | Progress, top risks, decisions needed | One-page dashboard | Fortnightly | PM |
| Departmental IT operations | Support implications, environment needs, runbook | Working session | Monthly, plus on change | Technical lead |
| Complaints officers | What is changing, training dates, feedback route | Workshop and pilot group | At milestones | Business analyst |
| Data protection officer | Evidence of data handling at design and release | Written review pack | Twice | PM |
| Situation | Escalate to | Within |
|---|---|---|
| A milestone will be missed by more than 5 days | Sponsor | 24 hours of the forecast being known |
| A suspected data-protection issue | Data protection officer and sponsor | Immediately |
| A change request exceeding delegated authority | Sponsor | At the next change meeting, or immediately if the work is blocked |
Note that the escalation rows specify a time limit and a threshold, and the review row for the data protection officer specifies two moments rather than a frequency. Both changes come from the same principle: the plan should be checkable. "Keep the DPO informed" cannot be verified and therefore cannot be missed — which is exactly why it is a bad entry.
Common mistakes¶
- Starting from a blank page instead of the stakeholder register. The result omits high-influence people and over-serves the ones already engaged.
- Frequency without an owner. A schedule of updates that nobody produces is a wish list.
- Vague escalation. Without a trigger, recipient, and limit, escalation happens late or not at all.
- Verbal decisions. Most "but we agreed…" disputes start in a corridor conversation; record decisions in the decision log.
- Over-communicating. Daily updates to a sponsor train them to stop reading, and the message that matters is lost in the noise.
- One channel for everyone. Some stakeholders will not use the tool you chose, and they will not tell you — they will simply be uninformed.
- Never revisited. The plan should change when the project changes phase or a stakeholder's attitude changes.