Project Dashboard¶
At a glance
- Purpose: Show the few measures that tell a reader whether the project is in trouble, on one page — with thresholds agreed in advance so the colour means something.
- Use it when: At every reporting cycle, for a steering committee or sponsor. It supplements the status report; it does not replace its narrative.
- Owner: The project manager; thresholds agreed with the sponsor.
- Related: Module 11 · Lab 18 · Lab 22
- Spreadsheet version:
csv/project-dashboard.csv
How to use this template¶
- Choose few measures — six to ten. A dashboard with thirty numbers is a data dump and will be read as one: nobody will notice which of them changed.
- Define thresholds before you need them. If the colour is chosen after seeing the number, the dashboard reports opinion, and the conversation becomes about the colour.
- Mix lagging and leading measures: cost and schedule variance are lagging; defect detection rate, requirement volatility, and blocked-work counts are leading.
- Show trend, not just level. A single Amber reading means little; three consecutive Amber readings mean the previous actions did not work.
- State what the reader should do. A dashboard that does not lead to a decision is decoration.
Field descriptions¶
| Area | Suggested measure | Threshold example | Watch out for |
|---|---|---|---|
| Schedule | Schedule variance, or milestone slip in days | Green ≤ 2 days, Amber ≤ 5, Red > 5 | Percentages that hide which milestone slipped |
| Cost | Cost variance, and cost performance index | Green ≥ 0.95, Amber 0.85–0.95, Red < 0.85 | Measures with no agreed currency or baseline |
| Scope | Requirements added or changed since baseline | Green 0, Amber ≤ 2, Red > 2 | Scope growth reported as progress |
| Quality | Open P1/P2 defects; defect escape rate | Green 0 P1, ≤ 2 P2 | Counting defects without severity |
| Risk | Open exposure above threshold; top risk trend | Green ≤ 2, Amber 3–4, Red ≥ 5 | Registers frozen at identification |
| Delivery | Items completed against forecast | Green ± 10%, Amber ± 20% | Forecasts without a stated basis |
| Team | Blocked work items; unplanned absence | Green 0 blocked, Amber ≤ 2 | Absence reported only after the fact |
| Stakeholders | Decisions outstanding beyond their due date | Green 0, Amber 1, Red > 1 | Decisions nobody recorded needing |
Blank template¶
# Project Dashboard — [Project name]
| | |
| --- | --- |
| **Period** | [Start] – [End] |
| **Prepared by** | [Who] |
| **Baseline reference** | [Baseline version and date] |
| **Overall** | [Green / Amber / Red] |
## 1. Measures
| Area | Measure | This period | Last period | Threshold (G / A / R) | Status | Trend |
| --- | --- | --- | --- | --- | --- | --- |
| Schedule | [Variance in days] | | | 2 / 5 / >5 | | |
| Cost | [Variance; CPI] | | | 0.95 / 0.85 / <0.85 | | |
| Scope | [Changes since baseline] | | | 0 / 2 / >2 | | |
| Quality | [Open P1 / P2] | | | 0 / 2 / >2 | | |
| Risk | [Open exposure ≥ threshold] | | | 2 / 4 / ≥5 | | |
| Delivery | [Completed vs forecast] | | | ±10% / ±20% / >20% | | |
| Team | [Blocked items] | | | 0 / 2 / >2 | | |
## 2. Top risks and issues
| ID | Item | Exposure or severity | Response | Owner | Trend |
| --- | --- | --- | --- | --- | --- |
## 3. Decisions needed from this forum
| Decision | Needed by | Options | Impact if delayed |
| --- | --- | --- | --- |
## 4. Milestones
| Milestone | Baseline date | Forecast | Variance | Status |
| --- | --- | --- | --- | --- |
## 5. What changed since last period
[Three or four sentences. If nothing changed, say so — a dashboard that is always the same colour is
either a stable project or an unread one.]
## 6. Data quality note
[Which measures are measured, which are estimated, and what is not being measured at all. A dashboard
should state its own limitations.]
## 7. Thresholds and their origin
| Measure | Green | Amber | Red | Agreed with |
| --- | --- | --- | --- | --- |
Worked example¶
From Lab 18, on the analytics dashboard project — invented figures for teaching:
| Area | Measure | This period | Last period | Threshold | Status | Trend |
|---|---|---|---|---|---|---|
| Cost | CPI | 0.94 | 0.97 | 0.95 / 0.85 | Amber | ↓ |
| Schedule | SPI | 0.92 | 0.98 | 0.95 / 0.85 | Amber | ↓ |
| Schedule | Milestone slip (days) | 3 | 0 | 2 / 5 | Amber | ↓ |
| Quality | Open P1 / P2 | 0 / 3 | 0 / 1 | 0 / 2 | Amber | ↓ |
| Risk | Open exposure ≥ 6 | 4 | 3 | 2 / 4 | Amber | ↓ |
Four measures degrading in the same period is a different situation from one, and the dashboard is built to make that pattern visible at a glance rather than across four paragraphs of prose. Even so, the numbers alone do not explain themselves:
- SPI is a ratio of value earned to value planned, so a front-loaded baseline makes it look better early and worse later. This project had exactly that baseline pattern, which is why the third row — a plain count of days slipped against a named milestone — is on the dashboard as a cross-check, and why the period-on-period movement matters more than the level. Lab 18 works this discrepancy through in full.
- The status column is deliberately all Amber. The project is not in crisis, and reporting Red would trigger escalation the project does not need. Where that line sits is a judgement, which is why the threshold table is part of the artefact.
Common mistakes¶
- Thresholds set after the fact. The dashboard then reports the reporter's comfort level, not the project's condition, and the discussion shifts to the colour.
- Too many measures. Attention is the scarce resource; six to ten is a practical ceiling.
- Only lagging measures. Cost and schedule variance tell you about the past. Add leading indicators such as defect detection and blocked work if the point is to act early.
- No trend column. A level with no direction is half the information.
- Percentages of unknown wholes. "80% complete" is meaningless without the basis of the percentage, which is why the schedule and cost rows use days and indices.
- No data-quality note. Readers assume measured precision where estimates are being reported.
- No decisions section. A dashboard that cannot produce an action is a report nobody needs.
- Aggregating the whole project into one colour. Combining scope, cost, and quality hides which dimension is failing — the same aggregation error as balancing only total resource capacity.