Change Request

At a glance

  • Purpose: Record a proposed change to an agreed baseline, force its impact to be estimated, and give one named person the authority to accept or reject it.
  • Use it when: Anyone asks for something that alters scope, schedule, cost, or quality after the baseline is agreed. Discussing it informally instead is how baselines quietly stop meaning anything.
  • Owner: The project manager assesses and records; the sponsor or change authority approves within agreed limits.
  • Related: Module 11 · Lab 19
  • Spreadsheet version: csv/change-log.csv

How to use this template

  1. Log first, discuss second. Giving the request an ID and a date means it cannot be absorbed silently, and it creates the audit trail that configuration management requires.
  2. Require an impact assessment before a decision: effect on scope, schedule, cost, quality, risk, and on other in-flight work. "It's small" is contradicted by the assessment or unnecessary to say.
  3. Put the change against the untouched baseline in the same units. Comparing a change against an already-overrunning plan makes every change look free.
  4. Record the decision, the reason, and the authority — including rejections and deferrals. A rejected request with a reason is a valuable artefact; an untracked one will be raised again.
  5. Present options, not a single price: do it now, do it later, do less, do something else instead. The value of the process is the comparison, not the arithmetic.

Field descriptions

Field What goes in it Watch out for
Change ID Stable reference (CR-007) Free-text change descriptions in email
Requester and date Who asked, and when Requests attributed to a department
Description What is being changed The reason smuggled in as justification
Reason The need, with any evidence "Management wants it"
Type Scope, schedule, cost, quality, technical, or regulatory Changes that are really defect fixes
Impact — scope Requirements added, changed, or removed Impact left to the reader to infer
Impact — schedule Days or dates, and whether critical-path work is touched Unsigned schedules
Impact — cost Money, at the same rates as the baseline Rates invented for the occasion
Impact — risk and quality New risks, testing consequences Registering only the benefit
Options Do now / later / reduce / alternative, with costs One option presented as the only choice
Recommendation The project manager's view and reason No recommendation, leaving the sponsor to guess
Decision Approved, rejected, deferred, and by whom "Approved" with no authority named
Baseline update What changed, when, and by whose authority Changes never reflected in the baseline

Blank template

# Change Request — CR-[nnn]

| | |
| --- | --- |
| **Raised by** | [Requester, role] |
| **Date raised** | [YYYY-MM-DD] |
| **Baseline affected** | [Scope / schedule / budget / all, with version references] |
| **Type** | [Scope / schedule / cost / quality / technical / regulatory] |
| **Current status** | [Submitted / assessed / decided / implemented / closed] |

## 1. Description of the change

[What is being changed, described precisely enough that an independent reader could implement it.]

## 2. Reason

[Why it is needed, and any evidence. State whether the need is new information, a correction of an
earlier assumption, a defect, or a preference.]

## 3. Impact assessment

| Dimension | Impact | Basis |
| --- | --- | --- |
| Scope | [Requirements added, changed, or removed, by ID] | [Requirements list] |
| Schedule | [Days, dates, and whether critical-path work is affected] | [Schedule version] |
| Cost | [Amount, in the baseline's currency and rates] | [Estimation basis] |
| Quality and testing | [Additional or reduced testing needs] | [Quality plan] |
| Risk | [New risks, and their exposure] | [Risk register entry] |
| Other work affected | [Dependencies, other projects, support] | [Dependency note] |

## 4. Options considered

| Option | Cost | Schedule effect | Benefit | Risk |
| --- | --- | --- | --- | --- |
| A — Do it now | | | | |
| B — Do it in the next phase | | | | |
| C — Do a reduced version | | | | |
| D — Do not do it | 0 | 0 | [Value forgone] | |
| E — Do something else instead | | | | |

## 5. Recommendation

[The project manager's recommendation, with the reason. Name the option, not a preference.]

## 6. Decision

| Decision | Decided by | Date | Conditions or follow-up |
| --- | --- | --- | --- |
| [Approved / Rejected / Deferred] | [Named person and role] | [YYYY-MM-DD] | [Conditions] |

## 7. Baseline update record

| Baseline document | Version before | Version after | Date | Authority |
| --- | --- | --- | --- | --- |

Worked example

From Lab 19, on the admission portal — invented figures for teaching. A change request arrives in week 9:

Dimension Impact Basis
Scope Adds requirement FR-12: applicants may amend a submitted application before the deadline Requirements matrix
Schedule +7 working days, of which 4 fall on the critical path via the eligibility rules engine Schedule version 1.0
Cost +[amount at the baseline day rate] for 7 person-days, plus 2 days of regression testing Estimation basis in the business case
Quality Two additional acceptance scenarios; the "immutable submission" rule must be reversed in the design Quality plan
Risk New risk: amendment history becomes an audit question, which the records office has not answered New register row, exposure 2 × 3 = 6
Option Cost Schedule Benefit Risk
A — Do it now 9 person-days +7 days Meets the applicant need before the window Audit question unresolved
B — Next release 8 person-days 0 Same benefit, after the admission window — effectively useless here Low
C — Reduced: amend only before submission is acknowledged 4 person-days +2 days Covers the common mistake case Low
D — Do not do it 0 0 Applicants must contact the office to correct details Support load rises

The recommendation would be C, because the underlying need — correcting a typo — is solved by C at less than half the cost of A, while A's schedule impact lands directly on the critical path identified in Lab 10. Presenting all four options is the point: a request carrying a single price invites a yes/no decision on someone else's framing.

Common mistakes

  • A verbal change absorbed into the work. By the time it is measured, the baseline has already moved and no one can say what it cost.
  • Impact assessed after the decision. An assessment produced to justify a predetermined answer is documentation, not analysis.
  • One option, one price. No comparison means no real decision.
  • Comparing against a slipped plan. Every change then looks affordable.
  • Costs in different units from the baseline. Rates created for the occasion are indefensible.
  • Rejections not recorded. They will return, and the reasoning will have to be reconstructed.
  • Confusing defects with changes. A defect against an agreed requirement is fixed through the defect process; a change to the requirement is a change request. Mixing them hides quality problems inside scope growth.
  • Baseline left stale. An approved change that never reaches the baseline documents reappears as an unexplained variance later.